The remaining wing of the original Oaklawn building has been removed. Drilling for the Geothermal wells will continue in that zone. With the exception of the second floor delivery hole, the building is completely enclosed with all exterior walls and glass in place. Flooring continues in the classrooms and Terrazo is finished on the second floor and in progress on the first floor. Drywall is complete and the DIRTT walls are being constructed between rooms. Ceiling tile and built in cabinets are also in progress. Basketball hoops and lights are in place in the gym. The media center ceiling is complete and ceiling work will commence in the cafeteria.
Oaklawn Elementary School
Wednesday, June 26, 2013
Monday, May 6, 2013
Construction Update May 6th 2013
Wall tile continues in the second floor bathrooms this week. The framing for the drop ceiling is being installed by a worker wearing stilts. The main library window is complete and framing is being installed on the north media center window. The learning center has half walls completed. Tables will be placed on each side to allow space for small groups to collaborate and use technology for research and preparing reports and presentations. Check out youtube.com/user/oaklawnoasd for walk through videos.
Sunday, April 28, 2013
Construction Update April 29th 2013
With the addition of the cafeteria walls and the roof, the building has taken full shape. Most of the drywall is complete in the office and some classrooms have painted walls. The large media center window is currently being framed to prep for glass. The gym is ready for concrete this week and the cafeteria floor will be close behind. Sams Well Drilling began the first of seventy wells last week for the Geothermal field. Each well in the loop will be about 300 feet deep. Take a look at the pictures and check out the You Tube link for the most recent video highlights.
Wednesday, April 17, 2013
Construction Update April 15th 2013
This week at Oaklawn the cafeteria structure and roof are in place, the brick work is going around the gym and exterior windows are mostly installed. The interior steps have concrete and are functional. Drywall continues to be installed in the office and throughout the building. Drilling for the Geothermal wells will begin soon. The south side fence playground fence will be moved north six yards onto the blacktop to create the space for the first series of wells. Footage in the YouTube video shows the area where the drilling will begin. Classroom and office loose furniture bids are being finalized and the library furniture is set.
Monday, March 25, 2013
Construction Update March 25th 2013
During the next week or two iron workers will be installing stairs (extension ladders and cranes are currently used to access the second level). The gym floor is scheduled to be poured in the next week, but is contingent on roof completion. Area B has exterior brick work on going with interior masonry on the second level. Exterior window installation will begin this week. Insulation and wood blocking is beginning on the first level in areas B and C.
Monday, March 11, 2013
Construction Update March 11th 2013
Work continues in the office area framing walls and installing electrical conduit. Entry ways to the first floor classrooms are being framed. Block and brick work continues on the south side of the building where the scaffolding is now located. The first look at the exterior and interior of the gym is available in the pictures below and on the you tube video. The space is being heated to prep the ground for concrete. The cafeteria walls will begin to be constructed in the next few weeks.
The pictures below: 1) a model of the block and brick work with spray foam installation, 2) The brick work being pressure washed to clean away debris, 3) second floor bathroom wall being constructed, 4) wide angle view of the gym
The pictures below: 1) a model of the block and brick work with spray foam installation, 2) The brick work being pressure washed to clean away debris, 3) second floor bathroom wall being constructed, 4) wide angle view of the gym
Sunday, March 3, 2013
Construction Update February 25th 2013
Brickwork is now complete on the three sides of the academic wing. The scaffolding has been relocated so the brick work is visible. This also means that the sidewalk on Linwood is open again to the public. Miron crews and our own Mr. Schneider have been working to remove the snow and ice to clean up the sidewalk for safe travel. When the ice is cleared, the buses will go back to dropping off and picking up at the regular location. This will create more space for parents to pick up in front of the school. Check back next week for updates on the gym.
Concrete is lifted up to the second floor by a crane and bucket. Check out the OWLS News Update for 2/25/2013 on youtube to see the video of the concrete being delivered to workers.
Concrete is lifted up to the second floor by a crane and bucket. Check out the OWLS News Update for 2/25/2013 on youtube to see the video of the concrete being delivered to workers.