During the next week or two iron workers will be installing stairs (extension ladders and cranes are currently used to access the second level). The gym floor is scheduled to be poured in the next week, but is contingent on roof completion. Area B has exterior brick work on going with interior masonry on the second level. Exterior window installation will begin this week. Insulation and wood blocking is beginning on the first level in areas B and C.