Wednesday, June 26, 2013

Construction Update June 26th 2013

The remaining wing of the original Oaklawn building has been removed. Drilling for the Geothermal wells will continue in that zone. With the exception of the second floor delivery hole, the building is completely enclosed with all exterior walls and glass in place. Flooring continues in the classrooms and Terrazo is finished on the second floor and in progress on the first floor. Drywall is complete and the DIRTT walls are being constructed between rooms. Ceiling tile and built in cabinets are also in progress. Basketball hoops and lights are in place in the gym. The media center ceiling is complete and ceiling work will commence in the cafeteria.