Electrical, plumbing and HVAC work continues inside the building on the first floor and work has begun on the second floor in the academic wing. The precast gym walls are being installed and braced.
Precast gym walls are being set.
The angle of this photo shows the block before and after it is ground to create the burnished look.
Electrical wire being run.
Block wall being constructed around plumbing for the bathroom.
Metal support beams will be covered with block.
No comments:
Post a Comment